Scheduling Lighting Demand Response

  1. In System Browser, select Project > Field Networks > [SORIS network] > [Enlighted adapter] > [energy manager] > Demand Responses.
  1. In the Extended Operation tab, specify the following settings:
  • Next to the ID property, enter the identifier of the demand response that you want to modify and click Save.
  • Next to the Duration property, enter a numeric value for the demand response duration and click Save.
  • Next to the Price Level property, select the wanted demand response price level and click Save.
  • Next to the Pricing property, enter a numeric value for the demand response pricing and click Save.
    This value is operational for the energy consumed during the demand response period.
  • Next to the Start Time property, select date and time for the demand response start and click Save.
  1. Next to the DR Configuration property, click Create DR.
  • System Browser refreshes and displays the new demand response schedule.